Veolia selected to deliver Springvale WTP

Veolia Australia and New Zealand has been chosen by Springvale Joint Venture and EnergyAustralia to deliver the new Springvale Mount Piper Power Station Water Treatment Plant (Springvale WTP).

Veolia will partner with Australian based Infrastructure Capital Group to fund the project, located in New South Wales’ Central West region.

The Mount Piper Power Station provides approximately 15 per cent of NSW’s power, and the Springvale WTP will be built under a build, own, operate and transfer contract.

Related stories:

It has been commissioned by EnergyAustralia and the Springvale Joint Venture.

This facility will treat the mine water and deliver water to the power station for beneficial reuse. The project aims to enhance the quality of mine water discharged, ensure operational compliance in relation to water outflows and enable continued operations of both the mine and the power station.

The project requirements include:

● Transfer of water from the Springvale Mine to EnergyAustralia’s Mount Piper Power Station
● Treatment and reuse of the mine water, which is to be used as the industrial cooling water for the power station as well as ensuring excess water discharge complies with relevant environmental obligations
● Implementing a brine extraction and crystallisation process that can blend with the waste streams from the Mount Piper Power Station, ensuring both the mine and the power station remain in operations.

Following the construction, Veolia will then be responsible for the operations and ongoing maintenance of the pipeline and treatment facility, over a 15-year period.

“Veolia’s expertise in water treatment as well as our strong presence in mining and infrastructure has given both the Springvale Joint Venture and EnergyAustralia the confidence to award this 15-year water infrastructure contract to Veolia, which is so important to NSW’s power supply and provides an environmental outcome that will guarantee the mine’s future,” said Doug Dean, Managing Director of Veolia Australia and New Zealand.

“This contract confirms the added-value solutions and expertise that our group provides to its energy and mining clients, so that their processes can comply with industry and regulatory standards and can improve the efficiency of their operations.”

While preliminary site activities have already commenced, this contract now allows construction of the Springvale Water Treatment Plant to proceed immediately and will be completed by mid 2019.

The contract is projected to generate a number of jobs in the regional area and approximately 400 million AUD in revenue for Veolia over the coming 17 years.