EPA Victoria orders recycler to stop accepting material

The Metropolitan Waste and Resource Recovery Group (MWRRG) is initiating a range of measures to support councils, following a EPA Victoria notice that SKM Services stop accepting recyclable material at its Laverton North site.

EPA issued the recycler with notices on 19 June that required it bring outdoor stockpiles at Maffra Street, Coolaroo and Laverton North into compliance with the Victorian Waste Management Policy by 3 July 2019.

An EPA media statement said regulatory action followed an inspection that revealed waste on site had increased following an extension of time for compliance.

Additionally, a fire broke out at the Laverton North site 9 July that EPA believes began on a conveyor belt.

“EPA is of the opinion that SKM understood its obligations under the notices, but had not demonstrated a move towards achieving compliance at the Laverton North site,” the statement reads.

“The company will still be able to process waste at its Laverton North site while the notice is in place, but will not be able to receive any new materials until EPA is satisfied that it has achieved compliance with the Victorian Waste Management Policy.”

MWRRG is seeking confirmation from SKM that it has alternative provisions in place to ensure it can continue to provide service to up to 10 affected local councils.

MWRRG CEO Rob Millard said MWRRG’s focus is on ensuring minimal disruption to residents by working with affected councils, other recycling facilities and landfill operators on immediate and long-term solutions.

“Following China’s decision to limit the importation of recyclables, MWRRG has been developing collaborative procurements for recycling services, working with 11 council clusters comprising more than 60 councils across the state,” Mr Millard said.

“By councils working together, larger contracts will be offered in the industry to encourage investment in recycling infrastructure and technology, and to attract new candidates to the Victorian recycling sector.”

Mr Millard said industry would be asked to provide expressions of interest on the collaborative procurements in August, with detailed submissions expected by the end of the year.